Project:
Realign Arc Light Bloulevard
Contracting Agency:
NAVFACMAR
Contract Amount: $5,704,913
Contract Type:
Firm Fixed Price
Prime or Subcontract Work: Prime
|
|
Description of Work:
The design-build, firm-fixed price roadway project included the construction of three roundabouts at Arc Light Blvd. with Marianas Blvd., Carolines Avenue with Chicago Avenue, and Chicago Avenue with Davis Avenue at Andersen Air Force Base, Guam. The project also widened Arc Light Blvd., Carlines Avenue and Chicago Aveneue thoroughfares by adding a median dividers, bike lanes and sidewalks.
Reliable Builders, Inc.'s design team included Engineering, Management and Planning Services Corporation (EMPSCO), Efren B. Santos and Wayne Wixon & Associates. Electrical works and landscaping works were subcontracted to small disadvantaged local companies.
With a contract amount of $5,704,913.00, RBI completed the project in 328 days with 53,616 man hours from December 2009 to October 2010.
|