Project:
Postal Center
Contracting Agency:
NAVFACMAR
Contract Amount: $3,769,685.13
Contract Type:
Firm Fixed Price
Prime or Subcontract Work: Prime
|
This is a firm-fixed price design-build project to construct a new single story Postal Service Center at Andersen Air Force Base, Guam with a building area of 481 square meters (5,177 s.f.) and new parking area of 2,625 s.y.
With an initial project contract amount of $3,655,206.63, Reliable Builders, Inc. completed the construction in 413 calendar days to include modifications and time extensions with a total contract of $3,769,685.13. Reliable Builders, Inc. self-performed 73% of the total contract amount.
The work includes design and construction of facility which includes post office boxes area for public areas, mail sorting and package storage areas, vault room, service counters, post master office, loading docks for delivery, all necessary utility rooms, toilets, delivery areas, detection and suppression systems, pavements and parking lots, associated site works, and all necessary supporting accessories for a complete and usable facility.
BUILDING FEATURES: • New Postal Service Center • Service Counter Lobby • Post Office Box Area (Lobby) • Work Room • Admin Offices • Delivery Vehicle Loading • Loading Dock • Outdoor Parcel Boxes • 44 Public Parking Areas • Controlled Access Gate • Electrical & Communication Room Mechanical Room
With an initial project contract of $4,083,000, Reliable Builders, Inc. completed the construction in 460 days with 83,498 man hours performed by RBI for approximately 25% of the contract amount of $1,127,063.00 from April 27, 2007 to July 31, 2008.
|